Work plan

Deadlines

Project Plan

Define your optimal sprint duration and plan your sprints until project end using Global Sprint Plan Table 1.

Table 1: Global Sprint Plan
Sprint Start Finish
01 10/3/2022 16/3/2022
02 17/3/2022 23/3/2022
03 24/3/2022 30/3/2022
04 31/3/2022 06/4/2022
05 07/4/2022 14/4/2022
Easter Break 14/4/2022 18/4/2022
06 19/4/2022 20/4/2022
07 21/4/2022 28/4/2022
Student Week Break 30/4/2022 8/5/2022
08 09/5/2022 11/5/2022
09 12/5/2022 18/5/2022
10 19/5/2022 25/5/2022
11 26/5/2022 01/6/2022
12 02/6/2022 08/6/2022
13 09/6/2022 15/6/2022
14 16/6/2022 22/6/2022
15 23/6/2022 30/7/2022

Build your project backlog, including all relevant tasks/deliverables, using Project Backlog Table 2. Prioritize all backlog items (PBI), keeping higher priority items at the top, and lower priority at the bottom.

Table 2: Project Backlog
PBI Title Status
A Global Sprint Plan Completed
B Gantt Chart Completed
C Research Completed
D State of the Art Completed
E Define Direction of Solution Completed
F System Diagramms & Structural Drafts In progress
G System Schematics & Structural Drawings In progress
H 3D Modelation To do
I Marketing Plan To do
J Eco-efficiency Measures for Sustainability To do
K Ethical and Deontological Concerns To do
L Interim Presentation To do
M List of Materials To do
N Video of the 3D Model To do
O Packaging Solution To do
P Functional Tests To do
Q Final Report To do
R Presentation To do
S Paper To do
T Poster To do
U Uploads To do

Plan each sprint at its beginning (Sprint Planning session) using the Sprint Plan Table 3.

Table 3: Sprint Plan 1
Sprint Task Duration (d) Responsible Involved
1 A 2 AR, FB AR, FB, TH, ZD & ZMD
1 B 2 FB AR, FB, TH, ZD & ZMD
1 C 5 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
1 D 2 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
1 E 1 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
Table 4: Sprint Plan 2
Sprint Task Duration (d) Responsible Involved
2 C 5 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
2 E 1 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
2 F 6 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
Table 5: Sprint Plan 3
Sprint Task Duration (d) Responsible Involved
3 F 3 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
3 G 6 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD
3 I 6 AR, FB, TH, ZD & ZMD AR, FB, TH, ZD & ZMD

Review each sprint at its end and update each item status on the Progress Register Table 6.

Table 6: Project Progress Register
Sprint PBI Responsible Involved Status
1 Z X and Y X, Y, Z, W Done
2 K Z X, Y, Z, W Done
3 D W, Y and Z X, Y, Z, W Done
4 A Y X, Y, Z, W Done
5 B Z and W X, Y, Z, W In progress
6 E X and W X, Y, Z, W In progress
7 C Y and Z X, Y, Z, W In progress

Identify key project deliverables (when they will be started and completed) and build a release Gantt chart.

Figure 1: Gantt chart Team4

gantt_chart_eps_team4.xlsx